No, as long as you have included an analysis of compliance with the enforceable policies and/or received any required permits; AND you have submitted any Necessary Data and Information as noted in the above question.
Department of Ecology
Shorelands and Environmental Assistance Program
Federal Permit Coordinator
Post Office Box 47600
Olympia, Washington 98504-7600
E-mail: ecyrefedpermits@ecy.wa.gov
For the length of the project.
Disagreements between federal agencies and the state on federal projects should be resolved through dialogue on the outstanding issues of a project with formal and informal mediation available as a forum for resolving disputes. Where a state objects to the issuance of a federal license or permit, the applicant may appeal to the Secretary of the U.S. Department of Commerce requesting an override of the state objection. See 15 CFR subpart H. Mediation is also a potential means for resolving a state objection and can be done in formal or formal venues.