Help/Assistance

For assistance information and materials please visit https://wsdot.wa.gov/business-wsdot/highway-access-requests-training/development-services.

Helpdesk phone:

WSDOT's Development and Local Agency Service staff are assigned to specific counties: See Notes/Comments below for more information.

Open an email to submit... [be sure and attach this document]

id: 2497

224-005 Access Connection Permit

Description/Purpose

To allow vehicular access and connection points of ingress to and egress from, the state highway system within unincorporated managed access areas that are under the jurisdiction of WSDOT.

Triggers and activities which would require this credential

It is required to have a WSDOT approved permit prior to constructing an access connection to a state highway.

Explanation/Description of costs/fees, including statutory, regulatory, or other legal authority for fees

Fee is based on Access Connection Category and type - See application for details as https://www.wsdot.wa.gov/publications/fulltext/forms/224-694.pdf

Application Information

The application is called 'DOT Form 224-694, Application for Access Connection Permit, Managed Access Highways Only' is online and can be accessed at https://www.wsdot.wa.gov/publications/fulltext/forms/224-694.pdf.

Yes- Additional items required are located on-line and on the second page of the application form: https://www.wsdot.wa.gov/publications/fulltext/forms/224-694.pdf

Yes - approval will be based on several factors, but center around safety of the public, applicant, and roadway at the requested access connection point. A meeting will be scheduled to overview the proposed Access Connection.

Applications are reviewed within the WSDOT regions, based on the location of the requested Access Connection. See Notes/Comments section below.

Once the permit is signed and the connection is built, the permit is valid. All connection permits issued by the department remain valid until revoked. The department may initiate an action to revoke any permit if significant changes have occurred in the use, design, or traffic flow of the property or of the state highway, requiring the relocation, alteration, or closure of the connection; if the connection was not constructed at the location or to the design specified in the permit; if the permit provisions were not met; or if the connection causes a safety, maintenance, or operational problem on the state highway system.

The right to an adjudicative proceeding can be requested within 30 days of a denial letter from WSDOT. WSDOT will notify the applicant of the date and time of the proceeding. WAC 468-51-150 explains the appeal process.

.
Permit Timeliness Results

Permit Timeliness data collection is in response to a State Auditor’s Performance Audit and RCW 43.42A. Each regulatory agency developed a plan to improve permit clarity, predictability, and timeliness. Each agency considers the customers experience to ensure permit assistance is simple to use, easy to access, and designed in a customer-friendly manner. Agencies report progress to the Governor’s Office for Regulatory Innovation and Assistance (ORIA). ORIA prepares and distributes reports, with participation from the State Auditor’s Office and Results Washington. See latest report here: https://www.oria.wa.gov/ORIA-2020-PermitTimelinessProgressReport.pdf.


Estimated Time Required By the Agency to Process a Permit Application (Definition)
Average days from Receipt to Complete: 38.2
Maximum days from Receipt to Complete: 304

Estimated Time Required By the Agency to Issue a Permit Decision (Definition)
Average days from Complete Application to Decision: 14.3
Maximum days from Complete Application to Decision: 43

(Summary results based on 29 submittals in 2024)

.
Legal authority
Notes / Comments

Construction must begin within ninety (90) days of the effective date of the permit and shall be completed within one hundred twenty (120) days of the issuance of the permit. WSDOT's Development and Local Agency Service staff are assigned to specific counties.

Visit https://wsdot.wa.gov/business-wsdot/highway-access-requests-training/development-services for a list of the region contacts.

Contacts
Washington State Department of Transportation
WSDOT Headquarters Mailing Address
Headquarters
310 Maple Park Avenue SE
P.O. Box 47300
Olympia WA 98504-7300
Email: hqcustomerservice@wsdot.wa.gov
Website: http://www.wsdot.wa.gov
Washington State Department of Transportation, Development Division - Snohomish & King Counties
15700 Dayton Avenue North
SnoKing Area, MS 240, P.O. Box 330310
Seattle WA 98133-9710
Email: pazookr@wsdot.wa.gov
Website: http://www.wsdot.wa.gov
Comment: Development Division Telephone: (206) 440-4710
Washington State Department of Transportation, Development Division - Island, San Juan, Skagit & Whatcom Co
1043 Goldenrod Road
Mount Baker Area, MS 210, Suite 101
Burlington WA 98233-3415
Email: stormer@wsdot.wa.gov
Website: http://www.wsdot.wa.gov
Comment: Development Division Telephone: (360) 757-5961
Washington State Department of Transportation, Development Division - Olympic Region
Website: http://www.wsdot.wa.gov
Comment:
Telephone: (360) 357-2736
Washington State Department of Transportation, Development Division - Southwest Region
Website: http://www.wsdot.wa.gov
Comment:
Telephone: (360) 905-2059
Washington State Department of Transportation, Development Division - North Central Region
Website: http://www.wsdot.wa.gov
Comment:
Telephone: (509) 667-2909
Washington State Department of Transportation, Development Division - Eastern Region
Website: http://www.wsdot.wa.gov
Comment:
Telephone: (509) 324-6199
* Credential details last updated 3/17/2022
[v3]