Oversize/Overweight Superload

Description/Purpose

A superload is a vehicle or combination with a non-divisible load having a gross weight exceeding 200,000 pounds and/or a total width or height exceeding sixteen feet and/or a load length exceeding one hundred and twenty-five feet. A Request for Approval of Oversize/Overweight Movement for loads over 200,000 must be submitted in writing and received at least 30 days before the proposed date of movement RCW 46.44.091(5). A Request for Approval of Oversize/Overweight Movement for loads over sixteen feet wide or sixteen feet high must be submitted in writing at least seven (7) calendar days before the proposed date of movement.

Once the Request for Approval of Oversize/Overweight Movement has been approved by the agency the carrier completes and submits the Oversize Overweight Load permit application (see above)

A request for approval of Oversize/Overweight Movement for loads exceeding sixteen feet of width, sixteen feet of height, and or 125 feet of load length must be submitted in writing at least seven (7) calendar days before the proposed date of movement.

Triggers and activities which would require this credential

As the title implies, this is a overweight or oversized permit for superloads, loads that exceed 200,000 pounds, and/or exceed 16 feet in height or width, and/or 125 feet load length. In order to ensure safety to the public, the highways systems and carriers, these permits require application at least 30 days prior to the movement date for overweight superloads and at least 7 days prior for overheight superloads.

Explanation/Description of costs/fees, including statutory, regulatory, or other legal authority for fees

Fee is based on weight over total registered weight at a fee per mile on State Highways. To Calculate estimated fee amount visit: https://wsdot.wa.gov/commercial-vehicle/permits/home

Application Information

The application is called 'DOT Form 560-021' is online and can be accessed at https://wsdot.wa.gov/travel/commercial-vehicles/commercial-vehicle-permits.

Yes - Prior to application for permit, a request for superload must include the following items: Applications in advance of movement date, as outlined above; evidence describing the purpose of the movement; item being transported must be clearly shown to be not divisible; A sketch of transporting laden vehicle showing axle loadings, axle space, tire size, tires per axle, width, height; evidence that shipper must review alternatives, if the load could be barged or shipped by rail; proposed route, to include railroad crossings; and traffic control plan, which must include impact to traffic, use of escort vehicles, railroad schedules, provisions for emergency vehicles to navigate around load. When request approved oversize overweight application can be submitted (see above).

Yes - approval is based on the bridge and pavement analysis and review of WSDOT Regions affected by the proposed move.

Superload requests and superload applications must only be submitted to the WSDOT Commercial Vehicle Services (CVS) Office for processing. Contact CVS at 360-704-6340 or at CVSPermits@wsdot.wa.gov.

Permits are valid for a single trip, up to three (3) days from the date of purchase

The permit may be further negotiated based on the analysis of the bridges and pavement. Further negotiations can include escort requirements, hours of movement, route, etc.

.
Permit Timeliness Results

Permit Timeliness data collection is in response to a State Auditor’s Performance Audit and RCW 43.42A. Each regulatory agency developed a plan to improve permit clarity, predictability, and timeliness. Each agency considers the customers experience to ensure permit assistance is simple to use, easy to access, and designed in a customer-friendly manner. Agencies report progress to the Governor’s Office for Regulatory Innovation and Assistance (ORIA). ORIA prepares and distributes reports, with participation from the State Auditor’s Office and Results Washington. See latest report here: https://www.oria.wa.gov/ORIA-2020-PermitTimelinessProgressReport.pdf.


Estimated Time Required By the Agency to Process a Permit Application (Definition)
Average days from Receipt to Complete: 1
Maximum days from Receipt to Complete: 1

Estimated Time Required By the Agency to Issue a Permit Decision (Definition)
Average days from Complete Application to Decision: 7
Maximum days from Complete Application to Decision: 22

(Summary results based on 2496 submittals in 2024)

.
Legal authority
Contacts
Washington State Department of Transportation, Commercial Vehicle Services
7345 Linderson Way SW
PO Box 47367
Tumwater WA 98504-7367
Email: CVSpermits@wsdot.wa.gov
Website: http://www.wsdot.wa.gov and Commercial Vehicle Services Webpage
Telephone: (360) 704-6340
* Credential details last updated 6/26/2025
[v3]