In addition to a complete JARPA form, you should include photographs of the project area, a vicinity map, and detailed drawings which clearly show the project and its location in relation to wetlands, creeks, rivers, or other waterbodies in the vicinity of the project area. Refer to the sample drawings and checklist on the Corps' Seattle District website.
If Endangered Species Act (ESA)-listed species or critical habitat may be affected by or occur in the vicinity of the proposed project, the Corps may need to consult with the National Marine Fisheries Service and/or U.S. Fish and Wildlife Service before making a permit decision. If consultation is required, you may need to prepare and submit a Biological Evaluation describing the impact your project would have on ESA-listed species and critical habitat, and proposed measures to minimize those impacts. Other Federal laws and tribal treaty rights can also affect permit decisions.
The expiration date of a permit is the date by which the work must be completed. Authorization under a Nationwide Permit or Regional General Permit generally expires when the general permit expires. General permits are issued for a period of 5 years, so authorizations are valid for shorter periods of time as the general permit nears its expiration date. Letters of Permission are normally issued for 3 years. Standard Individual Permits are normally issued for 3 to 5 years. In some cases, such as maintenance dredging, a standard permit may be issued for up to 10 years.
The terms and conditions of a proffered Letter of Permission or Standard Individual Permit may be appealed by the applicant under certain circumstances. Nationwide Permit and Regional General Permit verifications are not appealable. The Corps' Northwestern Division Engineer must receive a request for appeal within 60 days of the permit decision date.