After receipt of a complete application, the Corps' goal is to process the application within the following timeframes:
- Regional General Permit: 60 days
- Nationwide Permit: 60 days
- Letter of Permission: 120 days
- Standard Individual Permit: 120 days
However, the actual time to complete a permit decision on a particular application depends on the project's complexity, impact on the aquatic environment, affect on ESA-listed species, archaeological and/or tribal issues, Corps workload, and other factors.