Contact the appropriate Local Air Agencyfor more details about requirements. See the Links section below for more information
The notification must be postmarked 10 working days before the job's start date to allow Ecology to comment and/or schedule a site visit.
A working day means Monday-Friday and includes holidays that fall on any of the days Monday-Friday.
Submit asbestos notifications to the appropriate Local Air Agency and county planning agency. If Ecology is the local air agency, submit the notification to the correct Ecology regional office. Ecology's Industrial Section receives notices from their regulated businesses.
The job must be started and completed within the dates specified in the notice. If job schedules change, a change notice is required to be submitted.
Since there is no decision, an appeal is not applicable.