Submittal of a prospectus is the first step in the review process. The prospectus provides a conceptual overview of the proposed wetland bank and serves as the basis for initial public and Interagency Review Team review and comment.
The second step involves the development of a draft mitigation bank instrument which must be based on the prospectus. Agency acceptance of a Mitigation Banking Instrument (MBI) results in Certification issuance. A number of technical appendices need to be included with the MBI. The details of what is required in an MBI are included in
WAC 173-700-222.
A ‘Mitigation Banking Instrument Template’ and ‘Mitigation Bank Instrument Submittal Procedures and Checklist’ are available at:
https://ecology.wa.gov/Water-Shorelines/Wetlands/Mitigation/Wetland-mitigation-banking/Templates-guidance-documents.
Department of Ecology
Wetland Mitigation Banking Specialist
Shorelands and Environmental Assistance Program
P.O. Box 47600
Olympia, WA 98504-7600
Through the construction and operational life of the project.
You have a right to appeal Ecology’s decision to the Pollution Control Hearings Board within 30 days of the date of receipt of the decision. The appeal process is governed by Chapter 43.21B RCW and Chapter 371-08 WAC. “Date of receipt” is defined in RCW 43.21B.001(2).